Salinas draft plan would cut protected rustic land 28.47%, column says
A column in Claridad on November 18, 2026 argues that the draft revision of the Salinas land-use plan would cut the town's specially protected rustic land by 28.47% and open farmland, wetlands and a proposed nature reserve to construction.

The draft is the municipality's full revision of its Plan de Ordenamiento Territorial. The column, published in the paper's Comunidades section, says the plan's own diagnosis names severe flood risk, a water crisis and the loss of farmland, while several of its proposals would add to those pressures.
What the draft would reclassify
Citing Table 8 of the draft, the column says the area classed as Suelo Rústico Especialmente Protegido (SREP) would shrink by 28.47%, and its SREP-P category by 74.94%. It grants that a change of class does not by itself mean the land is lost or that every protection disappears, but says the scale demands an explanation of what changes and why.
The column lists more than 180 cuerdas in Ranchos Guayama that would move from SREP-P to urban land, about 50 cuerdas in Majada that would move from agricultural SREP to common rustic land, and unbuilt land in Río Jueyes that would move from SREP to urban land. It asks the agencies involved, the Planning Board among them, to weigh each change on its own and together before treating them as minor amendments.
A reserve the town once backed
The column's clearest case is the land between Villa Cofresí, Villa Esperanza and Urb. La Margarita, where a project known as Salmar was once proposed. In April 2023 the mayor sent the Senate a memorial supporting a community proposal to designate it the Reserva Natural Abey de Salinas, citing its forest, archaeological resources, wetland and high flood and tsunami risk, and asking that it keep its SREP class.
The draft now proposes to reclassify the same land as urban (R-I), which the column says would open it to construction.
Water, homes and farms
The column says the municipality proposes 1,564 new homes while the same draft records a steady population decline, a housing vacancy rate of 22.4% and limits in water and sewer service. It cites the plan's own finding that the Acuífero del Sur is the town's only source of drinking water and has suffered saltwater intrusion from overuse, and asks for an updated water balance before any expansion.
On farmland, it cites Agricultural Census figures in the draft showing that Salinas lost 1,552 cuerdas of farm area between 2012 and 2022. It asks that the CIRO and AES/Salinas Solar energy projects be weighed against that, noting that CIRO covers about 541 acres in a recharge zone of the aquifer.
The column also faults the draft for relying on 1971-2000 climate data and for lacking a fuller assessment of waste disposal after the municipal landfill's projected 2030 closure, and asks whether communities could study changes affecting hundreds of cuerdas before the phase I and II hearings, held on September 24, 2026. It calls for a moratorium on new construction projects and says the plan should not be approved until each change of class is backed by evidence.
Land on the market in Salinas
Ads for Salinas lots of 5 cuerdas or more ask from $100,000 to $12,000,000.
In Ranchos Guayama, a tract of 7.58 acres is advertised at $100,000, on the market since March 18, 2025; its ad cites nearby water and power connections. Near the top of the range, a 12-cuerda lot on PR-1 with frontage on the Caribbean is advertised at $10,000,000 and pitched for a tourism project.